Construction Begins on Parking Improvement System at El Dorado Nature Center 

By Staff Writer
Published on Thu, Nov 19, 2026

Heads up nature lovers—construction is beginning at El Dorado Nature Center parking lot as part of the City’s efforts to create a safer and more accessible experience for visitors. Construction will begin the week of Nov. 30 at the Spring Street entrance and Nature Center parking (Gate 1, Spring Street south) and is expected to continue through January.

The phased project began in 2025 with roadway resurfacing and parking lot enhancements inside El Dorado East Regional Park, which were completed in March 2026. The construction of the Nature Center parking lot is part of the Parking Management System phase of the project that will modernize aging payment systems, improve traffic flow, and provide a more efficient arrival experience. New sidewalks and pedestrian access paths will also be added to create a safer experience for pedestrians entering the park.

Since construction at Gate 1 is expected to last from December through January, the regular parking lot and main entry to the Nature Center may not be accessible during this time.

Map of El Dorado Nature Center

Visitors will be directed to park across Spring Street at the parking lot adjacent to the archery range located inside El Dorado East Regional Park, Area 2. Visitors may also need to travel upwards of half a mile, using the designated crosswalk at Spring Street and El Dorado Park Street, to enter through the alternate Nature Center entry located at the quarter-mile trail. A temporary ADA pathway will also be installed at the alternate entrance.

Visitors and participants of Nature Center programming and tours should anticipate using the alternate parking and entry locations and plan to arrive early. Visitors of Long Beach Animal Care Services and the community garden may still access those facilities through the normal entry.

Following the completion of construction at Gate 1, similar construction will occur at Gate 2 (main vehicle entry to El Dorado East Regional Park) followed by Gate 3 and Gate 4 located on Wardlow Road.

  • During Gate 2 (Spring Street north) construction - Vehicle entry to El Dorado East Regional Park will be rerouted to Gate 1 (Spring Street south) and use the Nature Center perimeter road into the park.
  • During Gate 3 (Wardlow Road south) construction - Park exit will be available through Gate 2 (Spring Street north) or Gate 4 (Wardlow Road north).
  • During Gate 4 (Wardlow Road north) construction - Park exit will be available through Gate 3 (Wardlow Road south) and Gate 2 (Spring Street north).

Once the Parking Management System phase is completed at all four entry points, anticipated for spring 2027, a new payment system will take effect. Additional information on the new payment process and vehicle entry fees will be shared publicly prior to implementation.

In addition, installation of new wayfinding signage at El Dorado East Regional Park is expected to begin by the end of 2026 and be complete by early 2027.

The El Dorado Park Paving, Wayfinding and Parking Management project is part of the City’s Elevate ‘28 Infrastructure Investment Plan and funded with support by California State Parks, the City’s General Fund and Measure A funds. These improvements are all part of the City’s efforts to make enjoying nature and the outdoors more accessible and enjoyable for the Long Beach community.

Heads up nature lovers—construction is beginning at El Dorado Nature Center parking lot as part of the City’s efforts to create a safer and more accessible experience for visitors. Construction will begin the week of Nov. 30 at the Spring Street entrance and Nature Center parking (Gate 1, Spring Street south) and is expected to continue through January.